Airports · 2020–2022
Air Traffic Control Tower, Radom
Air traffic control tower with Airport Fire Service, 3,902 m²: 15 kV/1 MW, 2×630 kVA substation, 900 kVA generator set, 4×75 kVA UPS.

Project description
Scope and solutions
Reconstruction of Warsaw-Radom Public Use Airport — construction of the Air Traffic Control Tower together with the Airport Fire Service and technical and road infrastructure (building B4, 3,902 m²). Detailed electrical design with specifications and approvals for general contractor ANNA-BUD (10.2020–01.2022): 15 kV supply system with 1 MW capacity, MV and LV cable duct system, 2×630 kVA transformer substation, 900 kVA generator set, 4×75 kVA, 50 kVA and 40 kVA UPS, supply to the server room, rack cabinets, PAŻP (Polish Air Navigation Services Agency) equipment, BMS automation, ventilation and air conditioning, normal and emergency lighting, reactive power compensation, lightning protection, earthing. Reference from ANNA-BUD (11.2022).
Reference letter — ANNA-BUD Sp. z o.o. (construction company)Air Traffic Control Tower with Airport Fire Station, Warsaw-Radom Airport · 2022
Projects
Other projects

Extension of the Wrocław-Strachowice passenger terminal — electrical and ELV systems, design in progress.

New Warsaw-Radom passenger terminal (30,000 m²): detailed design of electrical installations in 2D and 3D (Revit) for general contractor MIRBUD.

Buildings B1, B3 and K1 (7,600 m²): 15 kV/1.3 MW, 2×1250 kVA substation, 1,400 kVA generator set, 4×200 kVA UPS.
Contact
Planning a similar project?
Describe the building and the project stage — we will reply with a quote and a schedule within one working day.
Address
ul. Myśliwska 66/123, 30-718 Kraków, Poland
Office
Electrical department
ELV department
Telecommunications design
+48 533 317 286
HVAC automation & BMS
+48 507 874 718