Offices · 2010–2011
UKNF Headquarters, ul. Jasna 12, Warsaw
Reconstruction and extension of the UKNF office building (5,606 m²): 300 kVA UPS, 600 kVA generator set, 1000 kVA substation, server room (for Krib Sp. z o.o.).

Project description
Scope and solutions
Reconstruction, extension and modernisation of the office building at ul. Jasna 12 in Warsaw as the headquarters of the Polish Financial Supervision Authority (UKNF) — cubic volume 19,899 m³, 5,605.70 m². Design and cost-estimate documentation for technical security systems (access control, I&HAS, FAS, CCTV) and electrical installations with uninterruptible (guaranteed) power supply: 300 kVA UPS, 600 kVA generator set, MV supply line and 1000 kVA transformer substation; design work including revised drawings issued during construction, 03.2010–10.2011. Reference letter from the architect (11.2012).
Reference letter — ION Architekci (Łukasz Jaroszewski)Reconstruction and extension of the UKNF (Polish Financial Supervision Authority) headquarters, ul. Jasna 12, Warsaw · 2012
Other projects

Zachodnie Centrum Biurowe: ELV systems for a Class A office building — FAS, access control, CCTV, LAN, BMS.

LEED Platinum office building on ul. Bułhaka (PUU 5,125 m², 6 storeys, 86 parking spaces) — MV supply, substation, electrical, ELV systems, BMS.

Consultronix S.A. headquarters in Balice: MV service connection, transformer substation, electrical installations and ELV systems (building permit + detailed design).
Contact
Planning a similar project?
Describe the building and the project stage — we will reply within one working day and send a quote with a schedule within two working days.
The documentation they produced met the highest standards. (…) The design services provided by this team are worthy of recommendation to other organisations. (translated from Polish)
Talk to the designer
Address
ul. Myśliwska 66/123, 30-718 Kraków, Poland